Specifically, the consortium will design, supply, and install 5.4km of civil infrastructure, 10.8km of track, eight corresponding track turnouts, 10 stations and a maintenance centre.

The project is expected to last 20 months and will be completed in January 2019. The tramway is expected to be inaugurated in June 2019.