IN addition to the president of the republic, Brazilians elected representatives of the federal and state legislatives including state governors in elections held at the end of the October. In São Paulo, the richest state in the country and with the largest rail transport network, Mr João Doria of the incumbent Social Democrat party, which has been in power for 24 years, was elected for a four-year term.

Despite budget constraints following the recent economic crisis, railway development is one of the Doria government’s priorities and the administration is targeting expansion through public-private partnerships (PPPs).

The new governor wants to accelerate work already underway on the São Paulo Metro and Paulista Metropolitan Trains Company’s (CPTM) suburban network, as well as execute new projects to expand capacity and modernise existing lines.

The programme also proposes the construction of new light rail lines in major metropolitan regions outside São Paulo city and the introduction of an inter-city service between São Paulo, Campinas and Americana.

Mrs Roberta Marchesi, superintendent of the National Association of Passenger Rail Operators (ANPTrilhos), has a positive view of the new programme and the administration’s objectives.
“We believe that the new governor will enable the realisation of new projects,” Marchesi says. “It follows a more liberal economic line and investment will be reinforced mostly with the support of the private sector. We also have a very high expectation for medium-speed regional trains.”

Mr Clodoaldo Pelissioni, secretary of state for metropolitan transport with the São Paulo state government, explains that from January 2015 to December 2018, the state government invested Reais 17bn ($US 4.53bn), or an average of Reais 4.3bn a year. “With the works already completed, we will add between 500,000 and 700,000 new passengers per day to the metro and CPTM network,” Pelissioni says. “And with the projects set to be completed by 2020, there will be another 500,000 passengers. Today the rail network carries 7.5 million passengers per day and this is expected to reach 8 million by the beginning of 2019.”

Current work on the metro includes the extension of Line 5/Lilac. Nine stations were added in 2017 and 2018, two of which interconnect with Line 1/Blue and Line 2/Green, while a station at Campo Belo will open in early 2019 connecting with the future Line 17/Gold monorail which is also under construction. Concessions to operate these two lines were awarded to ViaMobilidade in August.

Line 17/Gold will have eight stations in this first phase and will run from an interchange with CPTM Line 9/ Emerald at Morumbi via Campo Belo on metro Line 5/Lilac to Congonhas station, near the airport of the same name, providing the first rail link to the city’s second airport.

Operations are expected to start in 2020 following a six-year delay. However, this now looks doubtful. Last month, Scomi, the Malaysian company responsible for building the monorail trains, signalled that it wanted to leave the consortium. The manufacturer has yet to start construction of an assembly plant while it has transpired that the cost of the project has increased by Reais 2bn to around Reais 3.7bn. São Paulo Metro was planning to meet the ViaMobilidade consortium at the end of November to try to find a solution.

The inauguration of CPTM Line 13/Jade earlier this year made it possible to introduce three services between the centre of São Paulo and Guarulhos International Airport, Brazil’s busiest, which was also not previously served by rail. According to Pelissioni, the project required an investment of Reais 2.1bn. “Of the 12km extension, 8km is an elevated line which crosses the Tietê River and highways,” he says. “For this, the largest viaduct was built as a curve and is 74m high and 690m long.”

The Airport Express provides a direct service five times per day, Monday to Friday, between Luz station and Guarulhos Airport with a journey time of around 35 minutes at a fare of Reais 8. The service travels over three CPTM lines: 11/Coral, 12/Sapphire and 13/Jade, with direct airport services coordinated with commuter trains.

There is also a direct stopping service between Brás and Guarulhos Airport, which currently only operates in the early morning and early evening. A half-hourly service is also available, but passengers have to change between lines 12 and 13 at Engineer Goulart. The Temoinsa-Sifang consortium is currently manufacturing eight trains with luggage compartments for exclusive operation on Line 13/Jade, which are expected to enter service in the second half of 2019.

Another project in the final phase of implementation is Line 4/Yellow, the first phase of which has been operated by the concessionaire ViaQuatro since 2010. The second phase comprises the construction of five stations, four of which have already been completed, the most recent being São Paulo-Morumbi in October.

Line 4 is 11.3km long and has 10 stations between Luz and São Paulo-Morumbi. With the addition of this station, São Paulo now has a 96km six-line network with 84 stations. According to Pelissioni, only Vila Sônia station will be pending in 2020 and the second phase is budgeted at Reais 1.9bn. When completed, the 12.8km Line 4 should carry 893,000 passengers per day.

Despite two stations opening on the initial 2.9km section in 2014, monorail Line 15/Silver had to wait four years for a four-station extension. The 4.7km link from Oratório to São Mateo opened in April this year and tenders are expected to be invited this month for a new contractor to complete work at four further stations as well as start work at Jardim Colonial. The contract will be signed in March 2019, with work commencing in April, and completion of the first station scheduled for October 2019.

This new tender is necessary because many construction companies cannot obtain finance to continue the works following the national Operation Car Wash corruption scandal which has gradually enveloped an increasing number of Brazilian companies and politicians since 2014.

According to Pelissioni, the metro’s new management is prioritising the completion of work on lines 4, 5, 15 and 17. In the case of CPTM, work is also set to resume on the 4.5km section of Line 9 from Grajaú to Varginha, which involves the construction of stations at Mendes-Vila Natal and Varginha. Work had been halted since the end of 2016 due to delays in the transfer of federal funds. A further Reais 945m is needed to build four road viaducts over the railway. “This is an important project as it serves a low-income peripheral region,” Pelissioni says. The extension is expected to open in 2020 and add 110,000 passengers to the 620,000 weekday passengers the existing 32.8km line already carries.

As well as new projects, Pelissioni believes the new government should continue to modernise the existing metro and CPTM networks. He says improvements have been carried out and that two-thirds of CPTM’s 94 stations are now accessible to disabled passengers with all set to be accessible by 2020.

In addition, delivery of 65 new metro trains will be completed in March, and he says a further 20 trains are required to expand CPTM’s fleet to the same size as that of the metro. “With a Reais 2bn investment, the next management team can complete these improvements,” Pelissioni says. “In the early 1990s, CPTM carried 700,000 passengers/day. Today, with practically the same network, there are three million passengers/day.”

CBTC

Regarding the metro, Pelissioni says that the refurbishment of 98 trains was recently completed and he expects installation of CBTC, which is already in use on Line 2/Green, to be extended to the entire network by 2020. “By 2019, it should be completed on Line 1/Blue and in 2020 on Line 3/Red,” he says. “We are also buying 38 sets of platform screen doors to prevent accidents, which will be installed on lines 1 and 3, and on the busiest stations on Line 2.”

One of the most anticipated future projects is metro Line 6/Orange. The 18.4km 17-station line will connect the northwest and eastern regions of the city, interchanging with several existing lines. “The problem is that the builders of the winning consortium (Move São Paulo) have not been able to obtain funding from Brazil’s National Bank for Economic and Social Development (BNDES) because of Operation Car Wash,” Pelissioni says. “We will annul the contract and launch a new tender in 2019.”

The project involves an investment of about Reais 10bn through a PPP, with the state of São Paulo paying Reais 1bn and the remaining Reais 9bn divided between private investors and the state government.”

Another planned scheme is the extension of Line 2/Green from Vila Prudente to Penha on Line 3/Red in the east of the city. The estimated cost of the extension is Reais 6.5bn. São Paulo Metro had obtained Reais 1.5bn from BNDES but decided to use the resources to complete Line 5/Lilac instead. Under a third stage, the idea is to extend the line north to the city of Guarulhos. These extensions will add 14km and 13 stations to Line2/Green, making it the longest metro line in São Paulo with a total length of 29km and 27 stations. Work is expected to start in 2021 or 2022.

The contract to build the 14km Line 18/Bronze monorail from Tamanduateí south to Djalma Dutra, in the centre of São Bernardo do Campo, was awarded four years ago. However, the Vem ABC consortium was unable to start work because it did not have the necessary land, while the federal government lacked the required funds for the project as it was trying to reduce its debt burden.

The plan now is to implement the Reais 6bn project as a PPP. The line will have 13 stations and is expected to carry around 320,000 passengers per day.

Even when all these projects are completed, São Paulo will still require more lines to plug gaps in the network and tackle the city’s chronic road congestion and pollution.

Light rail

Tenders for an extension to the Baixada Santista light rail line, which connects Barreiros, in São Vicente, and the port of Santos, with 15 stations, were republished last month after the Court of Auditors suspended the bidding notice and requested changes to the tender. A public session for the submission of proposals from prospective bidders is now scheduled for December 13 at the headquarters of the Metropolitan Urban Transport Company (EMTU) in São Bernardo do Campo.

The 8km extension with 14 stations will branch off the existing line at Conselheiro Nébias to serve the Valongo district in northern Santos. Work is expected to start at the beginning of 2019 and take two years to complete.

A third 7.5km extension with four stations is also planned. It will link the Barreiros area to Samaritá in São Vicente, which has a population of approximately 120,000 inhabitants.
These two extensions will expand the light rail network to 26km at a cost of about Reais 2bn.

Sorocaba is also planning a light rail line, and five companies are bidding for a contract to carry out a study into its implementation, operation and maintenance. The line will run from George Oeterer, in Iperó, to the district of Brigadeiro Tobias. Between 150,000 and 200,000 passengers per day are expected to use the line.

According to the City of Sorocaba, the 13km first stage of the project, scheduled to open in August 2020, will operate between George Oeterer and the centre of Sorocaba using an existing railway. A contract has been signed between the municipality of Sorocaba and Rumo allowing the municipality to operate LRVs on Rumo’s rail network. This will be the first time in Brazil that LRVs and freight trains will share the same tracks.

Rail development in greater São Paulo has experienced a mixed record in recent years. But with projects progressing at their own pace towards conclusion, the network is becoming better equipped to meet transport demand in this vast city region. Indeed, Marchesi says the electorate has given a clear signal for the introduction of a somewhat more liberal policy that prioritises acceleration of investment with the participation of the private sector under the supervision and regulation of the state. “This is how it works in all the major economies of the world,” she says. “In the coming years, Brazil may be in this same scenario and aligned with this development.”

São Paulo inter-city project gains momentum

THE Reais 20bn inter-city rail project, which calls for the construction of a 477km regional network in São Paulo state, with trains operating at a maximum speed of 140km/h, is expected to get off the drawing board soon.

The two lines will intersect in São Paulo and will serve 24 stations. The north-south line will connect Americana with Santos while the east-west line will run from Sorocaba to Taubaté. The network should directly and indirectly serve 173 cities and carry more than 170,000 passengers a day.

The 135km section between São Paulo, Campinas and Americana is expected to be built first. Trains will use the same tracks as CPTM’s Line 7/Ruby between São Paulo and Jundiai. From there to Americana new tracks will be laid parallel to an existing freight railway.

Pelissioni says the São Paulo - Jundiaí section will need additional tracks to enable fast inter-city trains to overtake much slower CPTM commuter trains. This will increase the cost of the project by Reais 5bn with the state contributing a third.

Rail freight concessionaire Rumo supports the introduction of the inter-city service between Jundiai and Campinas, because the line carries little freight traffic. However, this section does not have signalling and is unelectrified, so bi-mode electric-diesel trains are an option. It is a different story for the Campinas - Americana section as this line is heavily used by freight trains so investment in additional tracks would be needed.

Mr Vicente Abate, president of the Brazilian Railway Industry Association (Abifer), says that suppliers are counting on the inter-city project. “We know that the project between São Paulo and Campinas is already very mature,” he says. “Although the government has difficulty obtaining funding for its part in PPPs, solutions will have to be sought. Another way to look for funding is through real estate development next to the stations, as happens all over the world. The fact is we need medium-distance trains. Only Brazil, among the emerging countries, does not have this type of operation.”